Environmental Impact Assessment (EIA) Study

A defensible EIA report that answers the committee before it asks.

Professional fee
From ₹2,50,000
Govt. fees extra
Turnaround
120–240 days
Working days, typical
Authority
MoEFCC (Category A) / SEIAA (Category B) — prepared through a NABET (QCI) accredited EIA consultant
Validity
Terms of Reference are typically valid for 4 years as notified; baseline data should generally be no older than 3 years at the time of appraisal

An EIA study is the scientific backbone of your Environmental Clearance: one season of baseline data, impact prediction and an Environment Management Plan, prepared under Terms of Reference issued by the MoEFCC or SEIAA. We scope the study, run the monitoring through NABL-accredited laboratories and coordinate the NABET/QCI-accredited consultant so the report survives scrutiny at the Expert Appraisal Committee.

Legal basis: EIA Notification, 2006 (S.O. 1533(E)) and amendments, issued under the Environment (Protection) Act, 1986 and Rule 5 of the EP Rules, 1986

Who needs it

  • Projects listed in the Schedule to the EIA Notification, 2006 — mining, thermal power, cement, metallurgy, chemicals, pharma bulk drugs, refineries and distilleries
  • Category A projects appraised by the MoEFCC Expert Appraisal Committee (EAC) and Category B1 projects appraised by the State Expert Appraisal Committee (SEAC)
  • Building and construction projects above 20,000 sq m built-up area, and township or area development projects above 50 ha
  • Expansion or modernisation of an existing unit that crosses a Schedule threshold or materially changes the pollution load
  • Industrial estates, SEZs, ports, airports and highway projects that need a full or regional EIA
  • Promoters whose earlier EC was quashed or returned for want of adequate baseline data

Common in:Manufacturing & Industrial UnitsPharma & ChemicalsReal Estate & Infrastructure

Documents required

  1. 1Pre-feasibility report (PFR) and project layout on a 1:4000 or better scale map
  2. 2Form 1 (and Form 1A for building projects) as per EIA Notification, 2006
  3. 3Approved Terms of Reference (ToR) letter from MoEFCC / SEIAA
  4. 4Land documents, Khasra details and land-use certificate from the competent authority
  5. 5Toposheet showing the 10 km study area with eco-sensitive features marked
  6. 6Water source commitment letter and groundwater NOC (where applicable)
  7. 7Raw material, product and process details with mass balance
  8. 8Baseline monitoring data for air, water, noise, soil and biodiversity for one full season
  9. 9CER / EMP budget estimates and proposed green belt plan
  10. 10Risk assessment and Disaster Management Plan inputs (for hazardous processes)

Missing something? We help you obtain or regularise supporting documents before filing.

How we get it done

  1. 1

    Screening and scoping

    Week 1–3

    We classify the project under the Schedule (A / B1 / B2), identify the applicable general conditions such as proximity to protected areas or inter-state boundaries, and draft the Form 1 and PFR.

  2. 2

    Terms of Reference on PARIVESH

    Week 3–12

    The ToR application is filed on the PARIVESH portal and presented to the EAC / SEAC. We respond to the committee's queries and secure the ToR letter that defines the study.

  3. 3

    Baseline monitoring

    Month 3–6

    One full non-monsoon season (typically 3 months) of ambient air, surface and groundwater, noise, soil and ecological data is collected through NABL-accredited labs across the 10 km study area.

  4. 4

    Impact prediction and EMP

    Month 6–8

    Dispersion modelling, water balance, traffic and socio-economic assessments feed the Environment Management Plan with a costed budget for mitigation and monitoring.

  5. 5

    Draft EIA and public hearing

    Month 8–10

    The draft EIA and executive summary (in English and the local language) are submitted to the SPCB for a public hearing. We prepare the project team, record the proceedings and address every issue raised in the final report.

  6. 6

    Final EIA and appraisal

    Month 10–12

    The final EIA incorporating public hearing outcomes is uploaded on PARIVESH and presented to the EAC / SEAC for appraisal.

If you don’t comply

Starting construction without a valid EC based on a proper EIA is a violation of the EIA Notification and attracts prosecution under Section 15 of the Environment (Protection) Act, 1986 (imprisonment up to 5 years and/or fine up to ₹1 lakh, with additional daily fines for continuing offences). The NGT and High Courts have ordered stoppage of work, demolition and environmental compensation for projects that proceeded without clearance.

Why MYDA Group

  • Specialists, not generalists

    Environmental compliance is our only practice, so your file is handled by people who do this every day.

  • Fixed fee, written scope

    You know the professional fee and the statutory fees before we start. No surprise add-ons.

  • Inspection and audit-ready

    We prepare your site and team for the board visit or certification audit and attend it with you.

  • Lifetime reminders

    Every condition, return and renewal goes into your compliance calendar with alerts.

Frequently asked questions

Does MYDA Group prepare the EIA report itself?

EIA reports must be prepared by a consultant accredited by NABET under QCI for the relevant sector. We act as your project manager: we scope the study, engage and coordinate the accredited consultant and NABL laboratories, review every chapter for defensibility, and represent the proposal before the committee.

How long does baseline data take and can we skip the season?

The ToR normally requires one full season of baseline data, excluding the monsoon, which means a minimum of three months of continuous monitoring. The season cannot be skipped, but we can start monitoring in parallel with the ToR process when the scope is predictable, which often saves two to three months overall.

What is the difference between Category A and Category B projects?

Category A projects are appraised centrally by the MoEFCC's Expert Appraisal Committee and always need an EIA. Category B projects go to the State Environment Impact Assessment Authority; the SEAC decides whether a project is B1 (full EIA and public hearing required) or B2 (appraised on the basis of Form 1 and project documents without a full EIA).

Is a public hearing mandatory for every EIA?

A public hearing is required for all Category A and B1 projects, with specific exemptions listed in the Notification such as units within notified industrial estates that have themselves been through the clearance process, and certain expansion or modernisation cases. We confirm the applicability during scoping so there are no surprises later.

How old can the baseline data be?

Committees generally expect primary baseline data that is not more than three years old at the time of appraisal. If the project is delayed, we advise on whether a fresh season of monitoring or supplementary data will be needed before submission.

Often needed alongside

EIA & Clearances

Environmental Clearance (EC)

Prior Environmental Clearance is the statutory permission for any project listed in the EIA Notification, 2006 before construction or expansion begins. Whether your project is appraised centrally by the MoEFCC or by your State authority, we prepare the application on PARIVESH, present it to the committee, respond to each query and track the clearance until the letter is issued and conditions are mapped for compliance.

Starting price
From ₹3,00,000
Turnaround
90–240 working days

EIA & Clearances

Coastal Regulation Zone (CRZ) Clearance

Any construction or activity within the Coastal Regulation Zone — generally 500 m landward of the High Tide Line and along tidal water bodies — needs CRZ clearance under the CRZ Notification, 2019. We obtain the HTL/LTL demarcation and CRZ map from an authorised agency, prepare the application and take it through the State Coastal Zone Management Authority to the MoEFCC or State authority for clearance.

Starting price
From ₹1,25,000
Turnaround
90–180 working days

Pollution Control

Consent to Establish (CTE)

The Consent to Establish (CTE), also called the NOC to establish, is the first statutory clearance any new or expanding industry needs from its State Pollution Control Board before construction, land development or equipment installation begins. We categorise your unit correctly, build the technical file and handle the OCMMS filing and follow-up through to grant.

Starting price
From ₹20,000
Turnaround
30–75 working days