Waste Authorizations

Solid Waste Processing Facility Authorization

SPCB authorisation for MRFs, composting, bio-methanation, RDF and waste-to-energy plants.

Professional fee
From ₹45,000
Govt. fees extra
Turnaround
30–90 days
Working days, typical
Authority
State Pollution Control Board (SPCB) / Pollution Control Committee (PCC), in coordination with the urban local body
Validity
5 years (Form II authorisation), subject to renewal

Operators of municipal solid waste processing, treatment and disposal facilities — material recovery facilities, composting and bio-methanation plants, RDF and waste-to-energy units and sanitary landfills — need authorisation from the SPCB under the Solid Waste Management Rules, 2016, valid for five years, alongside their consents. We prepare the Form I application, coordinate with the urban local body and set up the annual reporting the Rules demand.

Legal basis: Rules 15, 16 and 24 and Schedules I and II of the Solid Waste Management Rules, 2016 under the Environment (Protection) Act, 1986; EIA Notification, 2006 (Item 7(i)) for common municipal solid waste management facilities

Who needs it

  • Private operators and concessionaires running MSW processing plants under PPP or municipal contracts
  • Urban local bodies setting up or upgrading composting, bio-methanation or landfill facilities
  • Material Recovery Facility and dry-waste collection centre operators
  • RDF and waste-to-energy project developers
  • Bulk waste generators — townships, campuses, industrial estates — setting up on-site processing above the thresholds
  • Construction and demolition waste processing facilities

Common in:Recyclers & Waste ProcessorsReal Estate & Infrastructure

Documents required

  1. 1Application in Form I with facility type, capacity, technology and site details
  2. 2Agreement or work order with the urban local body for waste supply and site
  3. 3Consent to Establish and Consent to Operate
  4. 4Environmental Clearance for common MSW management facilities covered under Item 7(i)
  5. 5Site plan showing buffer zone, tipping floor, processing units, leachate treatment and landfill cells
  6. 6Technology description, process flow and mass balance including rejects and their disposal
  7. 7Design of sanitary landfill as per Schedule I (liner, leachate collection, gas management, cover)
  8. 8Compost or RDF quality assurance plan against Schedule II standards
  9. 9Odour, vector and fire control measures and emergency response plan
  10. 10Constitution documents, PAN and authorised signatory letter

Missing something? We help you obtain or regularise supporting documents before filing.

How we get it done

  1. 1

    Scoping and applicability

    Day 1–5

    We confirm the facility type, whether Environmental Clearance is needed, and the consent and authorisation sequence for your state.

  2. 2

    Technical documentation

    Day 6–20

    Process design, mass balance, landfill and leachate design and quality assurance plans are compiled against Schedules I and II.

  3. 3

    Form I filing

    Day 21–23

    The authorisation application is filed with the SPCB along with consent applications where not already granted.

  4. 4

    Verification and grant

    Day 24–75

    We support the SPCB verification and queries; the Board is expected to decide within 60 days of a complete application and issues the Form II authorisation.

  5. 5

    Reporting systems

    Day 75–90

    Daily waste receipt records, compost and RDF quality testing, groundwater and leachate monitoring and the annual report cycle are set up.

If you don’t comply

Operating a solid waste processing or disposal facility without authorisation or in breach of Schedule I and II standards is punishable under Section 15 of the Environment (Protection) Act, 1986, and SPCBs levy Environmental Compensation on operators and local bodies — the NGT has imposed compensation of hundreds of crores on states for legacy dumpsites and unprocessed waste. Rejects dumped outside a sanitary landfill are a specific and frequently penalised violation.

Why MYDA Group

  • Specialists, not generalists

    Environmental compliance is our only practice, so your file is handled by people who do this every day.

  • Fixed fee, written scope

    You know the professional fee and the statutory fees before we start. No surprise add-ons.

  • Inspection and audit-ready

    We prepare your site and team for the board visit or certification audit and attend it with you.

  • Lifetime reminders

    Every condition, return and renewal goes into your compliance calendar with alerts.

Frequently asked questions

Does our composting plant need Environmental Clearance?

Common municipal solid waste management facilities are Category B projects under Item 7(i) of the EIA Notification, 2006 and generally need clearance from the SEIAA, though smaller decentralised facilities may fall outside the threshold. We check applicability before you commit to a timeline.

What annual reporting applies to the operator?

Under Rule 24 the operator submits an annual report to the local body (by 30 April), which the local body forwards to the SPCB and the state urban development department by 30 June; the SPCB consolidates to CPCB. Your operating records must be ready to support those figures.

What standards must compost and RDF meet?

Schedule II of the SWM Rules sets limits for heavy metals, pathogens and physical parameters in compost and specifications for RDF quality, and compost sold must also comply with the Fertiliser (Control) Order where applicable. Regular third-party testing is a condition of authorisation.